An update from the Hollywood Community Redevelopment Agency (CRA)

Hollywood Beach

Underground Utilities Phase IV and Streetscape Beautification

Construction of SR A1A Complete Street Project from Hollywood Blvd to Sheridan Street

·    85% of trench excavation for FPL conduit placement on west sidewalk completed.

·    Contractor currently working on the central business district close to Taylor Street

·    Pedestrian Light poles are being installed from Taylor Street to the North.

General Contractor is hosting a monthly Coffee with the crew.

·    Answer questions from business owners and residents.

·    Meet the Subcontractors for any information related to the project.

·    Next coffee with the crew is schedule for September 15th at Giorgio’s Bakery

Phase IV- E/W Streets, Streetends and Surf Road from Harrison Street to Magnolia Terrace

·    Design phase 90% Completed

·    Has been submitted to the City’s Building Department for review

·    CM@risk solicitation released

·    Evaluation committee to meet 9/2022 to rank CM@risk general contractor

Phase IV- SR A1A from Hollywood Boulevard to the Southern City Limits

·    Design phase 50% Completed

·    FDOT Landscape variance is currently under evaluation by FDOT